Software Increment Release Notes ================================ Increment ID: I06A1730 Date created: 05/05/00 CSR number: UT02910A, 50134745, 50317701, CM90368, UT00820 Title: ANX LC total fail, ANX x-con tool, & babbling modem interrupts. Detailed Description of Increment: ---------------------------------- This patch bundles fixes for three issues. The first is a problem where all LCs at all VMs go into a Total Fail state. The error is caused by an SMS message queue corruption. The corruption blocks guaranteed messages between the ABM and VMs. The second issue is a problem with babbling modem interrupts. The issue is a reduction or even degradation of real time by a modem that is babbling with erroneous data. The third issue is a problem using using the PCGUI cross connect button where a deny response error message is received. System Configuration / Shelf Type Requirements: ----------------------------------------------- ALL / NONE Increments Needed: ------------------ I01A1730 - I05A1730 Loads Affected: --------------- APU Installation Instructions: -------------------------- Download increment from the Web: Either a) download the increment directly to the /iswd directory on the OPC. b) download the increment to tape and insert into the OPC tape drive. Start up Incremental SW Del. from the Software Admin toolset on the OPC. Deliver the increment: 1) Select Deliver an Increment. 2) Type y to verify your selection. Verify the increment: 1) From the ISD main menu, select Display Increments. 2) Select Display to Screen. 3) Verify the increment delivered have the correct Title and Description. Also verify that their status is "READY TO APPLY". NOTE: If the increment is a Linecard only increment, the status will be "LOAD DELIVERED". 4) Press any key to return to the main menu. Apply the increment: 1) From the ISD main menu, select Apply an Increment. 2) In the list, select the number next to the increment you delivered. 3) Select on e of these options: 1) Apply to ALL NEs (to set the increment fully into the system) 2) Trial on one NE (to test the increment to ensure that it causes no problems) If you select option 2, a list of NEs in the span of control appears. From the list of NEs, select the number next to the one you want to test. A confirmation screen appears. 4) Type y to verify your selection. 5) When the application is complete, press any key to scroll through the Summary screesn until you return to the main menu. 6) From the main menu, select Display Increments. 7) Select Display to Screen. 8) Verify that the status next to each NE now reads "APPLIED" (or "TRIAL APPLIED" if you chose to run a test in step 3 above). IF THE INCREMENT INVOLVES THE APU YOU MUST DO THE FOLLOWING STEP Dump the image: 1) From the ISD main menu, select Dump an APU Image. 2) Select one of the valid load types that can be dumped. 3) Select one of the valid NEs matching your previous parameters. 4) Type y to verify your selection. 5) When the image is complete, press any key to return to the main menu. Test Instructions: ------------------ Two of the fixes cannot be readily verified other than through reproducing the problem. These are the SMS queue corruption and babbling modem issues. Since these error conditions are a degradation of service, it is suggested monitoring for recurrences of the issue and checking system integrity after patch application is the best method. The third issue is easily checked in PCGUI.